The CEO decides to change the terminology in Scrum to best fit their organization. What should the scrum master do?

Allow change of only the artifacts

Say NO - Scrum cannot have changed terms

Make sure the terms are consistent and change them Scrum does not focus on terminology

Explain that changing terms will cause confusion

Verified Answer
Correct Option - d

To get all Infosys Certified Advanced Scrum Master Exam questions Join Group https://bit.ly/infy_premium_group

We're passionate about offering best placement materials and courses!! A one stop place for Placement Materials. We daily post Offcampus updates and Placement Materials.

Qtr No. 213, New Town Yehlanka Indore 454775

admin@prepflix.in