The CEO decides to change the terminology in Scrum to best fit their organization. What should the scrum master do?
Allow change of only the artifacts
Say NO - Scrum cannot have changed terms
Make sure the terms are consistent and change them Scrum does not focus on terminology
Explain that changing terms will cause confusion