Stories planned for sprint were complex. But project has estimated them as quite simple. Developers stretched for sprint and completed stories. Project has not captured effort taken for development. Can project do better estimation for subsequent sprint?

No

Yes

Correct Option - a

To get all Infosys Certified Quality Professional - Certification Exam questions Join Group https://bit.ly/infy_premium_group

We're passionate about offering best placement materials and courses!! A one stop place for Placement Materials. We daily post Offcampus updates and Placement Materials.

Qtr No. 213, New Town Yehlanka Indore 454775

admin@prepflix.in