Steven, the Scrum Master, is approached by one of the Development Team members saying that they are not completing regression tests for all of the work they are performing to the level defined in the Definition of Done. They have discussed this with the Product Owner and decided to remove regression testing from the Definition of Done. Which two actions are the most appropriate for Steven to take?

  1. Reject the decision as the long term maintainability of the product will be negatively impacted by modifying the Definition of Done.
  2. Accept the decision as a mutual agreement has been made between the Development Team and the Product Owner
  3. Ask the Development Team and the Product Owner what problem they are trying to solve by altering the Definition of Done and removing regression testing from it and in what ways will this decision impact transparency and quality
  4. Ask the Development Team and the Product Owner if they are still able to produce potentially shippable product increments by altering the Definition of Done

Choose the option that represents the answer.

Options a and d only

Options a and c only

Options c and d only

Options b and c only

Correct Option - c

To get all Infosys Certified Advanced Scrum Master Exam questions Join Group https://bit.ly/infy_premium_group

We're passionate about offering best placement materials and courses!! A one stop place for Placement Materials. We daily post Offcampus updates and Placement Materials.

Qtr No. 213, New Town Yehlanka Indore 454775

admin@prepflix.in