In one of the Agile projects, there are 10 Sprints planned for the completion of a Release. The Release Burndown chart is updated at the end of each Sprint to help the project manager understand the progress of the overall Release. At the end of Sprint 6, the Release Burndown chart shows that the team would be left with additional 20 User Stories which they will not be able to complete in the current Release. What should be the BEST possible course of action for the team at this stage?

Team should inform the constraints to Scrum Master and should approach Product Owner to reprioritize the User Stories for the remaining Sprints
The Project Manager recognizes that this is a slippage from the Scrum team and should force them to work for extra hours to complete these additional User Stories within the current release
Scrum master discusses with the Scrum Team and identifies the reasons for not being able to meet the planned User Stories for the release and then escalates to Product Owner that the project is at High Risk
The Project Manager adds new engineers to the project immediately after Sprint 6 and allocates the User Stories to them for completing all the Product Backlog Items within the Release timelines
Verified Answer
Correct Option - a

To get all Infosys Global Agile Certification Exam questions Join Group https://bit.ly/infy_premium_group

We're passionate about offering best placement materials and courses!! A one stop place for Placement Materials. We daily post Offcampus updates and Placement Materials.

Qtr No. 213, New Town Yehlanka Indore 454775

admin@prepflix.in