A critical database server is down because of which the stability of the entire application is in High Risk. The fix for this issues has to be done as soon as possible by the DBA teams. As per Change Management, why type of change this is?

Emergency Change
Critical Change
Standard Change
Unique Change
Verified Answer
Correct Option - a